Shotesham Road – Work has completed under the 2 way lights on 13th May and the final two connections off Shotesham Lane will be completed by 18th May. Difficulties with access, existing services and concrete in the road make up has meant progress was slower than anticipated.
Caistor Lane – 600m left to complete, retuning at the end of the scheme 2017. The work in Caistor Lane ran over due to incorporating the waste water, footpath improvement and developer connections. Other work in the area which will be using Caistor Lane as a diversion route means we will have to return to complete this section at the end of the scheme.
Arminghall Lane – Last section of slip-lining and services transfers to be completed under 2 way lights. Start date 03rd May; duration 4 weeks.
B1332 – Main work along the B1332 will start on 23rd May, starting at the south end of the village on Bungay Road & The Street. The pipe will be laid up to the junction of Springfields & Devlin Drive, then work the way back down the road, connecting all the services pipes. This work will be interrupted to move up to the High School for the summer holidays in an effort to reduce congestion at this point. Temporary traffic lights will be used as the work moves along the length of the B1332.
Markshall Lane – Expected to start in September, the date will be confirmed following discussions with the farmer who currently requires twice daily access across the bridge.
Caistor Lane – 600m left to complete, retuning at the end of the scheme 2017. The work in Caistor Lane ran over due to incorporating the waste water, footpath improvement and developer connections. Other work in the area which will be using Caistor Lane as a diversion route means we will have to return to complete this section at the end of the scheme.
Arminghall Lane – Last section of slip-lining and services transfers to be completed under 2 way lights. Start date 03rd May; duration 4 weeks.
B1332 – Main work along the B1332 will start on 23rd May, starting at the south end of the village on Bungay Road & The Street. The pipe will be laid up to the junction of Springfields & Devlin Drive, then work the way back down the road, connecting all the services pipes. This work will be interrupted to move up to the High School for the summer holidays in an effort to reduce congestion at this point. Temporary traffic lights will be used as the work moves along the length of the B1332.
Markshall Lane – Expected to start in September, the date will be confirmed following discussions with the farmer who currently requires twice daily access across the bridge.