Search our site
Poringland Parish Council
  • Home
    • News
    • Anglian Water
    • Community Land Project
  • Parish Council
    • Your Councillors
    • Meeting Dates
    • Agendas
    • Minutes
    • Council Committees
    • Documents >
      • Data Protection >
        • Privacy Statements
      • Financial
      • Regulatory
      • Procedural
      • Newsletters
      • Miscellaneous
      • Openness and Transparency
    • Staff Vacancies
  • Covid19
    • Parish Facilities
    • Local Support
    • Finance & Funding
    • Support - Domestic Abuse
    • Support - Young Children
    • Support - Mental Health
    • Support - Adult Wellbeing
    • Volunteering
    • Public Transport
  • Neighbourhood Plan
    • Submission Versions (Reg 16)
    • Neighbourhood Plan Meetings
    • Neighbourhood Plan Contact Details
  • Community Centre
  • Cemetery
    • Cemetery Closure
  • Contact Us
  • Community Facilities
  • Allotments
  • Links

Progress Report: May 2016

16/5/2016

0 Comments

 
Shotesham Road – Work has completed under the 2 way lights on 13th May and the final two connections off Shotesham Lane will be completed by 18th May.  Difficulties with access, existing services and concrete in the road make up has meant progress was slower than anticipated.
Caistor Lane – 600m left to complete, retuning at the end of the scheme 2017.  The work in Caistor Lane ran over due to incorporating the waste water, footpath improvement and developer connections.  Other work in the area which will be using Caistor Lane as a diversion route means we will have to return to complete this section at the end of the scheme. 
Arminghall Lane – Last section of slip-lining and services transfers to be completed under 2 way lights.  Start date 03rd May; duration 4 weeks.
B1332 – Main work along the B1332 will start on 23rd May, starting at the south end of the village on Bungay Road & The Street.  The pipe will be laid up to the junction of Springfields & Devlin Drive, then work the way back down the road, connecting all the services pipes.  This work will be interrupted to move up to the High School for the summer holidays in an effort to reduce congestion at this point.  Temporary traffic lights will be used as the work moves along the length of the B1332.
Markshall Lane – Expected to start in September, the date will be confirmed following discussions with the farmer who currently requires twice daily access across the bridge.
0 Comments



Leave a Reply.

    Author

    Write something about yourself. No need to be fancy, just an overview.

    Archives

    February 2018
    January 2018
    December 2017
    November 2017
    October 2017
    September 2017
    August 2017
    June 2017
    May 2017
    April 2017
    December 2016
    October 2016
    September 2016
    August 2016
    June 2016
    May 2016
    April 2016
    November 2015

    Categories

    All

    RSS Feed

Welcome to our social media feed, why not follow us on facebook

Copyright Poringland Parish Council.  Community Centre, Overtons Way, Poringland NR14 7WB.  01508 492182; clerk@poringland-pc.gov.uk