B1332 – Work along the B1332 on the Norwich side of Framingham, has now been completed and the traffic lights will be removed from the highway.
Work will resume in January on The Street in Poringland, between Church Close and Saxonfields, working towards the Budgens roundabout. Temporary traffic lights will continue to be used, as the work moves along the B1332. Once this pipe line has been installed, we will return to Stoke Rd roundabout in Poringland, working our way up to and around the roundabout.
Shotesham Road – This work has now been completed and all properties have been reconnected to the water main. The final few connections at the top of the road will be made once the new main is fully installed on High Street/Bungay road.
Caistor Lane –To be complete at the end of the scheme, in July 2017.
Arminghall Lane – Following investigation work that took place, the last section of slip-lining and services transfers requires to be completed under a road closure. We are hoping to bring this work forward to March 2017.
Markshall Lane – Expected to start in conjunction with completing the work in Arminghall Lane in 2017.
Work will resume in January on The Street in Poringland, between Church Close and Saxonfields, working towards the Budgens roundabout. Temporary traffic lights will continue to be used, as the work moves along the B1332. Once this pipe line has been installed, we will return to Stoke Rd roundabout in Poringland, working our way up to and around the roundabout.
Shotesham Road – This work has now been completed and all properties have been reconnected to the water main. The final few connections at the top of the road will be made once the new main is fully installed on High Street/Bungay road.
Caistor Lane –To be complete at the end of the scheme, in July 2017.
Arminghall Lane – Following investigation work that took place, the last section of slip-lining and services transfers requires to be completed under a road closure. We are hoping to bring this work forward to March 2017.
Markshall Lane – Expected to start in conjunction with completing the work in Arminghall Lane in 2017.