B1332 – Main work along the B1332 started on 23rd May, at the south end of the village on Bungay Road. The first week involved marking out the routed and precisely locating the existing assets. The work had to be suspended for a week over half term as other works were happening in the local area.
The pipe is being laid up the road working towards the junction of Springfields & Devlin Drive. Once it is all installed we will work our way back down the road, connecting all the services pipes. This work will be interrupted to move up to the High School for the summer holidays in an effort to reduce congestion at this point. Temporary traffic lights will be used as the work moves along the length of the B1332.
Shotesham Road – This work has now been completed and all properties have been reconnected to the water main. The final few connections at the top of the road will be made once the new main is fully installed on High Street/Bungay road.
Caistor Lane –To be complete at the end of the scheme, in July 2017.
Arminghall Lane – Following investigation work that took place, the last section of slip-lining and services transfers requires to be completed under a road closure. This will also have to take place at the end of the scheme, in July 2017.
Markshall Lane – Expected to start in September 2016.
The pipe is being laid up the road working towards the junction of Springfields & Devlin Drive. Once it is all installed we will work our way back down the road, connecting all the services pipes. This work will be interrupted to move up to the High School for the summer holidays in an effort to reduce congestion at this point. Temporary traffic lights will be used as the work moves along the length of the B1332.
Shotesham Road – This work has now been completed and all properties have been reconnected to the water main. The final few connections at the top of the road will be made once the new main is fully installed on High Street/Bungay road.
Caistor Lane –To be complete at the end of the scheme, in July 2017.
Arminghall Lane – Following investigation work that took place, the last section of slip-lining and services transfers requires to be completed under a road closure. This will also have to take place at the end of the scheme, in July 2017.
Markshall Lane – Expected to start in September 2016.