W/C 11/09/2017
• We made good progress and began work in the junction of Caistor Lane using 3-way lights today. The team will be working on Saturday 16 September 2017 and we will continue six day working wherever possible for the remainder of the scheme.
Next week (w/c 11/09/2017)
• There is a lot of work to do in the junction- as well as the connections to properties from the new main in Norwich Road, we also need to make the connection to the new main in Caistor Lane, which requires installation of a 20metre section of pipe.
• We are expecting the work in the junction to continue throughout next week and possibly into the following week. However, best case scenario, we will be aiming to backfill and tarmac this section at the weekend.
• Once our work in the junction is complete, we will jump past the school and then continue southward on Norwich Road. We will return to complete the section in front of the school in the October half term.
• We made good progress and began work in the junction of Caistor Lane using 3-way lights today. The team will be working on Saturday 16 September 2017 and we will continue six day working wherever possible for the remainder of the scheme.
Next week (w/c 11/09/2017)
• There is a lot of work to do in the junction- as well as the connections to properties from the new main in Norwich Road, we also need to make the connection to the new main in Caistor Lane, which requires installation of a 20metre section of pipe.
• We are expecting the work in the junction to continue throughout next week and possibly into the following week. However, best case scenario, we will be aiming to backfill and tarmac this section at the weekend.
• Once our work in the junction is complete, we will jump past the school and then continue southward on Norwich Road. We will return to complete the section in front of the school in the October half term.