Friday - moved 2-way lights to Oak Avenue to complete the final service connection at this location. We will begin work on this connection tomorrow.
Sunday - Our site manager has discussed the Santa Run with the organiser, Tal Williams, and we have agreed to ensure that the path is kept clear and our team will act as marshalls to ensure participants safely pass our works. We will also begin the work at Elvins Garage in the footpath- no traffic management will be required at this location but the lights will still be in place at Oak Avenue.
Monday -Complete Oak Avenue connection and reinstate road surface.
Tuesday- Move three-way lights back to the Footpath to complete the connection to the village hall.
Wed, Thurs , Fri- We will be working in the footpath alongside The Street, installing the main in the path towards Springfields, where we will complete the connection.
I haven't yet been given details of next weekends work so I will update you on this in next Fridays update- depending on the weeks progress it may not be required. There shouldn't be any traffic management in place from Wednesday 06 December onward, unless there ae any unforeseen circumstances.
Friday - moved 2-way lights to Oak Avenue to complete the final service connection at this location. We will begin work on this connection tomorrow.
Sunday - Our site manager has discussed the Santa Run with the organiser, Tal Williams, and we have agreed to ensure that the path is kept clear and our team will act as marshalls to ensure participants safely pass our works. We will also begin the work at Elvins Garage in the footpath- no traffic management will be required at this location but the lights will still be in place at Oak Avenue.
Monday -Complete Oak Avenue connection and reinstate road surface.
Tuesday- Move three-way lights back to the Footpath to complete the connection to the village hall.
Wed, Thurs , Fri- We will be working in the footpath alongside The Street, installing the main in the path towards Springfields, where we will complete the connection.
I haven't yet been given details of next weekends work so I will update you on this in next Fridays update- depending on the weeks progress it may not be required. There shouldn't be any traffic management in place from Wednesday 06 December onward, unless there ae any unforeseen circumstances.